Construction Projects

General Information

Corona del Mar - Sports Fields

Two Field Option
Project Overview:
Newport-Mesa Unified School District (NMUSD) is working to construct various upgrades to the sports field at Corona Del Mar High School (CdMHS). The project would facilitate various functions, some of which currently occur off site.

On October 24, 2017, the Board of Education approved the Final Environmental Impact Report.  The Board has authorized Staff to begin the design process for Option B, depicted above.  Option B includes two synthetic turf fields, one rubber track, sports lighting and spectator seating. The project is currently beginning the design phase which is expected to take a year.

Current Project Documents:

Corona del Mar Sports Field Project Fact Sheet (revised 10/17/2017)

Final Environmental Impact Report (October 2017)

Recirculated Draft Environmental Impact Report (August 2017)

* Please note:  Hard copies of the RDEIR will not be provided. You may download a copy from the link above, or come in to the District Office or the CdMHS Administration Office to view a copy.

Archived Project Documents:

Initial Study (February 2016)

Recirculated Initial Study (March 2016)

Notice of Availability of the Draft Environmental Impact Report*

Draft Environmental Impact Report (February 2017)

Notice of Improvement (September 13, 2017 - Information Meeting) 

* Please note:  Hard copies of the DEIR will not be provided. You may download a copy from the link above, or come in to the District Office or CdMHS Administration Office to view a copy.

Estancia High School - Reopen 25 Meter Pool

Estancia HS Pool
Project Update:

The existing pool at Estancia High School is now open for use.

Estancia High School - 50 Meter Pool

Project Description:

Project includes removal of the existing Estancia High School pool and installation of a new 50 meter pool and support facilities.  The District is currently working to obtain a design-builder.

Estancia High School - Security Fencing

Project Description:

Repair and upgrades of existing site fencing.

Public Meeting: 

Date:   Monday, October 29, 2018
Time:   6:00 pm – 7:00 pm
Place:  Estancia High School – Library
            2323 Placentia Ave.
            Costa Mesa, CA  92627

Estancia High School - Theater

Planning has begun on a new theater for Estancia High School.  The district has received and is evaluating architect proposals.

2018 HVAC Upgrades

Project Description:

Heating, Ventilation and Air Conditioning (HVAC) projects include the complete replacement of systems at various schools.

HVAC Unit

HVAC UnitBelow is the Newport-Mesa Unified School District's anticipated phased-in plan for installing Heating, Ventilation and Air Conditioning (HVAC) in all schools and district facilities.  Please note that the following schedule is tentative and subject to change due to varying unforeseen factors.

HVAC Anticipated Schedule
SCHOOL HVAC NOTES
California Yes Completed Summer 2015
TeWinkle Yes Completed Summer 2015
Killybrooke Yes Completed Summer 2015
Early College HS Yes Completed as part of modernization in 2016
Paularino Yes Completed Summer 2016
Sonora Yes Completed Summer 2016
Adams Yes Completed Summer 2016
Victoria Yes Had HVAC prior to projects
Rea Yes Had HVAC prior to projects
Eastbluff Yes Had HVAC prior to projects
Andersen Yes Had HVAC prior to projects
Lincoln Yes Had HVAC prior to projects
Newport Coast Yes Had HVAC prior to projects
Estancia HS Yes Had HVAC prior to projects
Corona del Mar MS/HS Yes Had HVAC prior to projects
Davis Magnet Anticipated Completion 2018 In construction - expected completion date 8/24/18
College Park Anticipated Completion 2018 In construction - expected completion date 8/24/18
Wilson Anticipated Completion 2018 In construction - expected completion date 8/24/18
Pomona Anticipated Completion 2018 In construction - expected completion date 8/24/18
Kaiser Anticipated Completion 2018 In construction - expected completion date 8/24/18
Woodland Anticipated Completion 2018 In construction - expected completion date 8/24/18
Whittier Anticipated Completion 2019  
Mariners Anticipated Completion 2019  
Newport Heights Anticipated Completion 2019  
Ensign Anticipated Completion 2019  
Newport El Anticipated Completion 2019  
Harbor View Anticipated Completion 2019  
Back Bay HS Anticipated Completion 2019  
Costa Mesa MS/HS Anticipated Completion 2020 Partial HVAC; full HVAC anticipated 2020
Newport Harbor HS Anticipated Completion 2021 Partial HVAC; full HVAC anticipated 2021

 

*Please find Community Meeting notices and presentations below

Woodland HVAC Public Meeting Notice (February 26, 2018)

Woodland HVAC Public Meeting Presentation (February 26, 2018)

Kaiser HVAC Public Meeting Notice (February 28, 2018)

Kaiser HVAC Public Meeting Presentation (February 28, 2018)

Pomona HVAC Public Meeting Notice (March 1, 2018)

Pomona HVAC Public Meeting Presentation (March 1, 2018)

College Park HVAC Public Meeting Notice (March 6, 2018)

College Park HVAC Public Meeting Presentation (March 6, 2018)

Wilson HVAC Public Meeting Notice (March 7, 2018)

Wilson HVAC Public Meeting Presentation (March 7, 2018)

Davis HVAC Public Meeting Notice (March 8, 2018)

Davis HVAC Public Meeting Presentation (March 8, 2018)

Wilson Elementary School - Admin and Fence

Construction has begun to reconfigure the admin area and site fencing for Wilson Elementary School.  Anticipated completion date is August 24, 2018.

Project Documents:

Wilson Fencing - Notice of Community Information Meeting - Jan 10, 2018

Wilson Fencing - Community Information Meeting Presentation - Jan 10, 2018

Contact Us

Ara Zareczny
Director, Facilities Development, Planning and Design
azareczny@nmusd.us
714-424-7522

Flavia Mendez
Administrative Assistant
fmendez@nmusd.us
714-424-8934

Steve Morris
Facilities Planning Coordinator
smorris@nmusd.us
714-679-9891

Mark Manstof
Facilities Analyst
mmanstof@nmusd.us
714-424-7567