Current Construction Projects

Under Construction

Overview: 

Replacement of scoreboards at EHS Jim Scott Stadium, CMHS Baseball and installation of new scoreboard at CdM Softball Field.

Status November, 2021:

CMHS - Scoreboard to be installed week of 10/18/21.  Anticipated completion November, 2021.

CDMHS - Scoreboard to be installed week of 9/13/21.  Anticipated completion October, 2021.

EHS - Scoreboard to be delivered to site week of 10/20/21.  Anticipated completion December, 2021.  Existing scoreboard remains in place until new scoreboard is completed.

Documents:

N/A

Planning Phase

Overview

Field area improvements for access and functionality.

Status November, 2021:

Project scope is currently being considered and will be defined once final approval has occurred.  This includes coordination with the school site and stakeholders.  The final scope will be presented at a future community meeting.

Documents:

N/A

 

Overview

Expansion of existing parking lot including new parking stalls and alterations for an accessible pedestrian path from parking lot to administration building.

Status November, 2021:

Phase One (anticipated Fall, 2021) consists of removal of portable building located off 18th Street.  Phase Two (anticipated Summer, 2022) will include construction of expanded parking lot and accessible features.

Documents:

N/A

Overview

Replacement of new ground flush mounted lifts for school busses and white fleet.

Status November, 2021:

CEQA exemption Board approved 9/14/21.  Project is currently in design with construction anticipated Summer of 2022.

Documents:

N/A

EHS Theater RenderingOverview:

Planning continues on a new theater for Estancia High School, which is expected to include a new 350 seat theater, black box, lobby and support spaces. 

Status November, 2021:

Project is DSA approved, and the Board approved construction management team is SafeworkCM.  Staff is preparing budget and schedule update (for Board approval), contractor pre-qualification packages, and bid documents.  Staff continues to update the EHS administration on the overall schedule, and are coordinating the relocation of current activities for construction of the new theater.  This will allow construction to begin as soon as the Board approves the construction contract.

Documents:

Theater Board Presentation - 10/7/19

Theater Board Presentation - 11/17/20

Theater Board Presentation - 11/17/20 - Meeting

Theater Community Meeting Presentation - 12/03/20

Overview

Project includes modernization of the existing courtyard in the middle of the Home Arts Building at Newport Harbor High School. This includes improvement in accessibility, drainage, landscaping as well as the kiln yard, equipment and roof structure.

Status November, 2021:

Budget was Board approved 7/13/21.  Project is in DSA review.  Anticipated construction to begin Summer, 2022. 

Documents:

N/A

Overview

Following the newly installed aquatics scoreboard, this project includes the installation of shade structures as well as replacement of bleachers and sports lighting.  

Facilities meets with school administrators on a regular basis, and the site administrators will have details on this project that will be shared with all stakeholders.

Status November, 2021:

The project is in design.  The budget for this project was Board approved July 13, 2021, and the architect design contract was Board approved August 17, 2021.  Construction anticipated to begin Summer, 2022.  Construction to continue during the 2022-23 school year, with anticipated completion Winter, 2022-23.

Staff will coordinate with NHHS administration and the City of NB for closure of the pool for the duration of the construction project.  All aquatic programs for the school and the City will need to be relocated during construction.

Documents:

N/A

Overview:

As a result of removal of trees on campus to accommodate the new Cliff Drive Pick-Up / Drop-Off Lot, the board approved on May 29, 2020 the recommendation to create additional enhanced outdoor student gathering areas within the campus. 

Status November, 2021:

Design is anticipated to begin Fall 2021, and Facilities will coordinate with school site administration and stakeholders.  Staff will present the proposed scope and anticipated budget to the Board for approval at a later date.  In addition, staff will present the design at a community meeting.  A construction schedule will be developed once the final scope is Board approved.

Documents:

N/A

Overview:

Expand sidewalk and landscaping improvements between the campus perimeter fence and adjacent streets at Corona del Mar High School and Ensign Intermediate. 

Status November, 2021:

Budget was Board approved 10/17/21.  The project is in design and staff will coordinate with school administration and the City of Newport Beach.  In addition, staff will present the design at a community meeting.  A construction schedule will be developed once the final scope is Board approved.  

Documents:

N/A

School Year Notes
Adams 2015  
Andersen 2015  
TeWinkle 2015  
Victoria 2015  
Newport Heights 2018  
Mariners 2018  
Wilson 2018  
Ensign 2019  
Corona del Mar       2019  
Future
School Year Notes
Back Bay TBD  
California TBD  
Costa Mesa TBD  
Davis TBD  
Harper Assessment TBD  
TeWinkle TBD  

 

Contact Us

Ara K. Zareczny, LEED AP
Administrative Director,
Facilities Development, Planning & Design
azareczny@nmusd.us
714-424-7522

Lori Horrell
Administrative Assistant II
lhorrell@nmusd.us
714-424-8934

Steve Morris
Facilities Planning Coordinator
District Project Inspector 
DSA #5981
smorris@nmusd.us
714-679-9891

Jaime Vejar, Jr.
Facilities Analyst
 jvejar@nmusd.us
714-424-7567